New sidewalk planned on Turk Hill Road

Approved

Outcome

September 9, 2026: the Town Board created the $1.3 million capital project and authorized construction bids, 5-0. The $887,190 transfer from the Sidewalk Reserve is subject to a 30-day permissive referendum.

Still to come: Construction bids; construction expected in 2027

Decided by the Perinton Town Board.

What this means

The Town Board has funded new and replaced sidewalk on Turk Hill Road toward the Community Center and authorized construction bids. Construction is expected in 2027; nothing is built yet.

Where it stands

  1. Proposed
  2. Hearing scheduled
  3. Under review
  4. Approved
  5. Under construction
  6. Completed

Turk Hill Road is getting about 4,600 feet of new and replaced sidewalk, from Summit Street in the village to the Perinton Community Center and Town Hall, with construction expected in 2027. The Town Board funded the project and authorized construction bids on September 9, 2026; nothing has been built yet.

The plan includes a pedestrian bridge over a tributary to Thomas Creek. The $1,300,000 budget (Capital Project 44) combines $307,000 in committed Monroe County sidewalk funding, $105,810 already set aside for engineering and $887,190 from the town's Sidewalk Reserve. The Sidewalk Reserve transfer is subject to a 30-day permissive referendum. Bid results and construction dates haven't been posted.

Where this comes from

Checked · Suggest a correction