Perinton town road paving and chip sealing, 2026

Completed

From the Town of Perinton.

What this means

The town's 2026 paving and chip sealing are done for the season. Chip sealing on Sully's Trail is on hold.

Where it stands

  1. Proposed
  2. Hearing scheduled
  3. Under review
  4. Approved
  5. Under construction
  6. Completed

The Perinton Highway Department finished its 2026 town road work: milling and paving on three groups of streets and chip sealing on 42 streets. The town lists Sully's Trail chip sealing as on hold.

Milling and paving

  • Wakeman Road: milling May 11 to 13, paving May 18 to 19.

  • South Ridge Trail and Lodge Pole Road: concrete gutter replacement June 8 to 26 (moved from May 18 to June 19), milling August 17 to 18, paving August 24 to 28.

  • Crystal Spring Lane, Shelter Creek Lane and Brookside Drive: concrete gutter replacement June 22 to July 10, milling August 3 to 4, paving August 11 to 13.

Chip sealing

  • Section 1: Country Downs Circle, Foxpointe Circle, Bell Flower Circle, Wood Lily Lane, Fellows Road, Huber Road.

  • Section 2: Raymond Road, Glen Circle, Pleasant Way, Fair Way, Malin Lane, Sandy Hill Drive, Sunny Brook Lane, White Oak Lane.

  • Section 3: Wickford Way, Weyburn Way, Duncott Road, Oakwood Lane, Hickory Lane, Salem Court, Blanford Lane, Red Oak Drive, Mill Road, Bending Oak Drive, Little Acorn Circle, Sully's Trail (on hold), Cambric Circle, Burnley Rise, Lands End, Whittlers Ridge, Tippet Way, Brannigans Cut, Simsbury Lane, Amity Court, Mattock Place.

  • Section 4: Stream View Circle, Steel Road, Bluhm Road, Mason Road, Royal Drive, Nobleman Court, Monarch Drive.

County and state roads in Perinton are on their own project pages, linked from the town page.

Where this comes from

Checked · Suggest a correction