Sewers approved for 52 properties now on septic
Approved
What this means
Perinton approved public sewers for 52 properties on Pilgrim and Woodcrest Circle, Briarwood Lane and Garden Drive that now use septic systems. It could still go to a referendum, and no construction date is set.
Have your say
The public hearing was held September 21. The approval is subject to a 30-day permissive referendum: it goes to a public vote only if a valid petition is filed in that period. For details, call the Town Clerk's office at Town Hall, (585) 223-0770, as listed on Town Board agendas.
Where it stands
- Proposed
- Hearing scheduled
- Under review
- Approved
- Under construction
- Completed
Perinton's Town Board has approved public sewers for 52 properties on Pilgrim and Woodcrest Circle, Briarwood Lane and Garden Drive that now use septic systems. The board voted on September 21, 2026, after a public hearing. It can still go to a public vote if a valid petition is filed within 30 days of that vote, and no construction date has been set.
The town estimates the average yearly cost at $293.55 for a typical property that connects and $117.89 for one that does not. The whole project is estimated at $7,712,700, paid with a bond through the sewer district.
The work adds 3,800 feet of sanitary sewer, replaces 4,600 feet of storm sewer and rebuilds the roads. Formally, it is Jefferson Avenue Sewer District Phase 2, Extension No. 74 to Perinton Consolidated Sewer District No. 8.
Where this comes from
- Town of Perinton: Town Board meeting minutes (draft), September 21, 2026 · perinton.gov
- Town of Perinton: Town Board meeting agenda, September 21, 2026 · perinton.gov
Checked · Suggest a correction