type: Civic Update
title: Storm sewer work on Lancashire Way
update_kind: project
stage: approved
next_milestone: >-
  Temporary road and gutter repair in late fall 2026; permanent repair in spring
  2027
plain_language: >-
  Lancashire Way stays open during the work, with one lane of alternating
  traffic. The town expected to start in late August or early September and to
  take one to two weeks.
official_url: >-
  https://perinton.gov/departments/public-works/highway/highway-maintenance/state-and-county-road-projects/
checked_on: '2026-10-04'
tags:
  - roads
  - construction
sources:
  - resource: >-
      https://perinton.gov/departments/public-works/highway/highway-maintenance/state-and-county-road-projects/
    title: 'Town of Perinton: Town, County, and State Road Projects'
generated:
  by: 'process:hm-schema-v2-p2'
  at: '2026-10-04T17:38:08.024Z'
superbee_updated_by: 'process:hm-schema-v2-p2'
topics:
  - roads
---
# Storm sewer work on Lancashire Way

The Town of Perinton is putting 220 feet of new 24-inch storm sewer pipe under the pavement on a short stretch of Lancashire Way, all inside the town's right of way. The road stays open with one lane of alternating traffic. The town planned to start in late August or early September and expected the work to take one to two weeks. It has not posted whether the pipe work is finished.

The road and gutters get a temporary repair in late fall, and a permanent one in spring 2027.